T. BHAIJI
Index SHEET 05 / 06

2 MW MV/LV distribution design

The PD Gemini building at TU Eindhoven is being renovated and its electrical system redone to current EU standards. I led load analysis and equipment selection across 13,600 m² and five floors, from W/m² estimates to a 2000 kVA transformer.

20 kV vacuum CB · 125 A 2000 kVA · Dyn5 400 VMAIN LV SWITCHBOARDGUPScriticalbypassBASEMENT + GF≤ 50 circuitsFLOOR 1≤ 50 circuitsFLOOR 2a≤ 50 circuitsFLOOR 2b≤ 50 circuitsFLOOR 3 · MECH≤ 50 circuits 13 600 m² · five floors · 2 MW
MV/LV single-line diagram as specified.
Sheet
05 of 06
Title
2 MW MV/LV distribution design
Client
Royal HaskoningDHV
PD Gemini renovation, TU Eindhoven
Drawn
Sep 2024 – Jan 2025
Work done
Power systems · Load and capacity planning · IEC compliance
Project type
Group project, 5 students
My role
Project Lead, load analysis and equipment selection
Status
DESIGN STUDYnot a built installation
IEC 60364 · IEC 60909 · IEC 62439 · Load flow · Excel modelling

You cannot size a transformer from a floor plan

The brief was clear about the goal, a compliant electrical system for the whole building, and silent about every number needed to get there. What existed was floor plans. What was needed was a grid connection, an MV level, a transformer rating, switchgear, panel positions and a circuit schedule.

The chain between those is unforgiving, because each step compounds. A room misclassified at the start propagates into a W/m² estimate, into a floor total, into a maximum demand figure, into breaker sizing, into panel count, into the size of the room the equipment has to physically fit inside. Errors early are not small later; they are safety hazards or expensive change orders.

And the factors that convert an installed-load estimate into real maximum demand (utilisation factor, power factor, transmission losses) are not something you invent. Getting defensible values was its own task.

From square metres to switchgear, one defensible step at a time

  1. We turned the floor plans into a spreadsheet per floor, with room number, name, area, likely loads and category, then redrew the plans against a shared colour legend. Making the classification visual is what made it reviewable: a wrong colour on a plan is obvious in a way that a wrong spreadsheet row is not.
  2. With a W/m² figure per room category, load totals follow per room, per category and per floor, covering lighting, small power and mechanical systems. Mechanical came out as the largest category, which is exactly the number the mechanical team was supposed to supply and did not.
  3. Utilisation factor, power factor and transmission losses convert estimated load into maximum demand in kW and then kVA. We did not pick these; our coach pointed us at the relevant IEC standards and we took defensible values from them. That is the only way the resulting transformer rating means anything.
  4. Maximum and nominal current on the LV side drive breaker and panel sizing; on the MV side they size the switchgear and set the grid connection and MV voltage level. Short-circuit calculation follows IEC 60909.
  5. Panel placement met physical reality repeatedly. LV sub-panels cap at 50 circuits each and are positioned for feeder and branch cable length and for maintenance access. The ground floor had no room for its panel, so it sits in the basement; the second floor took two panels to keep branch runs short; the third floor got a dedicated panel for mechanical loads. We proposed floor layout changes where nothing else would fit.
  6. In the main LV room, switchgear, UPS and busbars are arranged for space, cable routing and maintenance access, with the transformer in a corner behind a barrier so it is not reachable by unauthorised people. The block diagram separates critical from non-critical loads, shows generator and UPS ties, and applies IEC 62439 redundancy thinking with breakers and a bypass.
Headline equipment specified
Main transformer2000 kVA20 kV / 400 V, Dyn5
MV switchgear20 kV, 125 Avacuum circuit breaker
Building area13 600 m²five floors
LV sub-panels≤ 50 circuitsper panel
StandardsIEC 60364 / 60909 / 62439installations, short-circuit, redundancy

A complete, compliant design package, delivered on time

Outcome
2000 kVAtransformer specified, 20 kV/400 V Dyn5
13 600 m²load-analysed floor by floor, room by room
5floors of panel placement, with layout changes proposed
Weeklydocumented and presented to the client throughout

Every deliverable in the brief was completed inside the September-to-January window: requirements analysis, load calculation, capacity planning, equipment layout, main LV room layout, equipment selection and the MV/LV block diagram, documented and presented weekly, with safety and IEC compliance carried through rather than checked at the end.

The instructive part was the missing mechanical loads. The mechanical team never delivered the values we needed, and mechanical was the single largest load category. We estimated them from comparable projects with our coach's input and kept going, flagging the assumption rather than hiding it. That is the second project where an undelivered dependency was the critical-path risk, and it is why I now plan a fallback for external inputs before I need one.

SCOPE AND LIMITATIONSThis is a design study carried out as a student project with Royal HaskoningDHV, not a built and commissioned installation. Mechanical load values were estimated from comparable projects because the mechanical team did not deliver them.

Book a call

Happy to talk about a graduation internship, a vacancy, or a project you want a second opinion on. Twenty minutes is usually enough to work out whether it is worth a longer conversation.

Typical length
20 to 30 minutes
Time zone
Central European Time, Arnhem
Languages
English, Hindi
Usually free
Weekday evenings and most of the weekend

Looking for a graduation internship from February 2027.

Power electronics, embedded hardware, renewable energy or power systems. I am equally happy writing the firmware and tooling around them. Based in Arnhem, open to relocating in the Netherlands.

Based in
Arnhem, Netherlands
Available
Graduation internship from Feb 2027

© 2026 Tanishq Bhaiji · Arnhem tanishqbhaiji42@gmail.com LinkedIn CV (PDF)